80kVA / 128–209kWh High-Voltage C&I BESS
Flexible battery-energy configurations for commercial peak shaving, solar integration and medium-duration energy management.
View 80kVA / 128–209kWh System →Reduce peak grid demand, manage high-load periods and improve energy flexibility with commercial and industrial battery energy storage systems engineered around the site's actual load profile, grid-import target and required discharge duration.
Peak shaving uses a Battery Energy Storage System (BESS) to supply part of a facility's electrical demand when site load rises above a predefined utility-grid import target. Instead of drawing the entire peak from the grid, the battery discharges to support the facility load.
During lower-demand periods, the battery can recharge from the utility grid or from available on-site solar PV. The Energy Management System (EMS) coordinates battery charging and discharging according to site demand, battery state of charge, grid limits and the selected operating strategy.
The correct peak-shaving system should therefore be selected from both required discharge power in kW and usable battery energy in kWh, not from nominal battery capacity alone.
Site meters and the EMS monitor facility demand, grid import and configured operating limits.
When facility demand approaches the configured grid-import target, the EMS calculates the required battery response.
The PCS converts battery DC energy to AC power and supports the site load, reducing utility-grid import.
The battery can recharge during lower-demand periods or use available solar generation in preparation for the next demand peak.
The BMS manages battery operating limits and protection. The EMS uses site-meter data to coordinate the battery and PCS according to the configured grid-import target and peak-shaving strategy.
Use stored energy during high-load periods to reduce maximum grid import.
Support demand-management strategies where the applicable commercial tariff includes demand-based charges.
Support short-duration facility loads above the preferred grid-import level.
Store available surplus PV generation and use the energy during later demand.
Coordinate charging and discharging across different operating or tariff periods.
Depending on system architecture, the same BESS platform may support additional energy-management functions.
Required BESS power is primarily determined by how much site peak demand needs to be reduced. Required battery energy is then determined by how long that reduction must be sustained.
| Design Factor | Why It Matters |
|---|---|
| Site Peak Load (kW) | Defines maximum site electrical demand. |
| Target Grid Limit (kW) | Defines the preferred maximum utility-grid import level. |
| Required BESS Power (kW) | Peak demand minus target grid limit provides a preliminary power requirement. |
| Peak Duration (h) | Determines how long the required BESS output must be sustained. |
| Usable Battery Energy (kWh) | Approximately power × duration before project-specific margins. |
| Reserve & Efficiency | DoD, losses, auxiliary consumption, degradation and reserve affect installed capacity. |
| Daily Peak Frequency | Affects SOC strategy, cycling and battery availability. |
| Solar PV Profile | Shows whether available PV energy can recharge the battery. |
| Electricity Tariff | Helps determine whether peak shaving, load shifting or a combined strategy should be evaluated. |
Assume an industrial facility normally operates below 400kW but experiences production peaks approaching 500kW for approximately two hours.
In this simplified example, the BESS should provide approximately 100kW for 2 hours, giving a preliminary usable-energy requirement of approximately 200kWh.
Final installed capacity should also consider allowable depth of discharge, PCS efficiency, battery losses, auxiliary consumption, reserve margin, operating temperature, degradation, peak frequency and end-of-life requirements.
Read the Complete C&I BESS Sizing Guide →
Final selection depends on required peak-reduction power, discharge duration and operating reserve. These three platforms cover common medium-scale commercial and industrial peak-shaving requirements.
Flexible battery-energy configurations for commercial peak shaving, solar integration and medium-duration energy management.
View 80kVA / 128–209kWh System →125kW liquid-cooled platform for industrial peak reduction, load management and medium-duration BESS applications.
View 125kW / 232.9kWh System →Higher-energy reserve for industrial peak shaving, solar integration and multi-mode C&I energy management.
View 125kW / 261.2kWh System →A commercial peak-shaving project should be configured around the actual electrical system, facility load curve and operating objective. Useful engineering inputs include:
Peak shaving is not controlled by battery capacity alone. The EMS uses site-meter data and system status to determine when the BESS should charge, remain idle or discharge.
After defining the load profile and preliminary peak-reduction target, use the dedicated BESS engineering resources for detailed sizing and technical-document review.
Peak shaving is often combined with solar integration, industrial load management, EV charging or microgrid operation. Review the related application pages according to the project objective.
Send your facility load profile, peak demand, target grid-import limit, transformer capacity, electricity tariff, solar PV capacity and required operating strategy. The project can then be reviewed for suitable BESS power and battery-energy requirements.
Request a Peak Shaving BESS Proposal →